Belagavi Smart City 4th-Annual Report -Completed, In Progress, Tendered, DPR, PPP Projects

  • MAJOR EVENTS OCCURRED DURING THE YEAR 2019-20

The Company being a Special Purpose Vehicle created for implementation of smart city project in the city of Belagavi, the Company will plan, appraise, approve, release funds, implement, manage, operate, monitor and evaluate the Smart City development projects.

  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal
  • Belagavi Smart City,belagavi smart city proposal pdf,Belagavi Smart City 4th-Annual Report,Belagavi Smart City Annual Report,Belagavi Smart City projects,belgaum smart city projects,belagavi smart city project,Belagavi Smart City upcoming projects,Belagavi Smart City tendered projects,Belagavi Smart City PPP projects,Belagavi Smart City On going projects,Belagavi Smart City completed projects,Smart City,smart city in india,smart city mission upsc,smart city project,smart city ranking in india 2021,smart city portal

1st April 2019-31st March 2020 : During the period under review, Company has taken up the following projects. Details are as under –

Name of the ProjectSCP CostWO CostPresent Status
1Energy Auditing of Street Lights under Smart City Energy efficiency program.0.230.23Work Completed
2Road Side Drinking Water Kiosks (Phase I)0.400.38Work Completed
3Rain water harvesting & Composting Facility in Parks0.100.08Work Completed
4Theme Based Park – NathPai Garden1.060.92Work Completed
5Smart Bus shelters with dedicated bus bay (Phase I – 5 Bus Shelters of A category)2.001.91Work Completed
6Rehabilitation of Stray Cattle0.740.64Work Completed
7Heritage Park – Phase I Water Body & Check Dam4.273.95Work Completed
8Smart Class rooms Phase I Part A3.202.75Work Completed
9Smart Class rooms Phase I Part B0.720.61Work Completed
10Trauma Centre Part A1.851.31Work Completed
11Procurement of Digital Bill Board0.940.71Work Completed
12Sanitary vending machine and incenirator0.330.31Work Completed
13Development of Smart Class room Phase II Part A (Civil)0.360.34Work Completed
14Development of Smart Class room Phase II Part B (ICT)1.111.03Work Completed
Total17.3115.17

WORK IN PROGRESS/ON GOING (Rs. In Cr)

Name of the ProjectSCP CostWO Cost
1Construction of two Smart roads at KPTCL road and Mandoli road (Variation included)25.0023.51
2Appointment of System Integrator for establishment of Common Command & Control Centre76.8045.99
3Command and Control Centre Building3.352.99
4Smart Roads at Dharmanath Area (Package I) (a)A Type (withDucting):2.475 Km47.0043.64
5City Bus Terminal33.5032.23
6Kanbargi lake rejuvenation & recreational spaces5.004.47
730 bed Maternity Hospital at Vantamuri2.752.33
8Smart Roads at Srinagar Area (Package II) (a)A Type (with Ducting):1.85Km(b)B Type (without Ducting):1.57Km47.343.58
9Smart Roads at Shahpur Area (Package IV)(RTO to Jijamata Circle, Veg Market Road, Kapileshwar Colony, SPM Road, Mahatma Phule Road, Shukrawar Peth Road)B Type (without Ducting) : 5.43 Km37.3934.03
10Smart Roads at Tilakwadi Area (Package V)(Congress Road, Mandoli road to 1st gate, Mandoli road to 2nd gate, Nanavadi Road)A Type (with Ducting) : 5.65 Km43.5037.96
11UG – LT Cabling Package I (Srinagar Nagar)7.757.19
12UG – LT Cabling Package II (Mahantesh Nagar)7.226.7
13UG – LT Cabling Package III (Anjaney Nagar)8.908.27
14Smart Bus Shelter Phase II5.004.8
15Smart Bus Shelters (PAN) Phase III2.001.74
16Procurement of Traffic Signals under ITMS3.001.7
17Construction of Cycle Track and Footpath from Ashoka Circle to Surabhi Hotel (NMV Package I)6.906.13
18Heritage Park – Phase II18.5518.62
19Parking for Private buses2.001.96
20Development of Modern Market at Tilakwadi (Kalamandir)47.346.69
21Smart Roads at Ramteerth Nagar Area (Package III) (4.4 Km)27.6923.03
22White Topping of Roads Package-1 [NH (Near KLE Hospital) to Kolhapur Circle, Kolhapur Circle to Rani Chennamma Circle, Kolhapur Circle to Sangolli Rayanna Circle-]38.831.30
23White Topping of Roads Package-5 [ Road from APMC-Junction toKangrali KH]12.7411.22
24Construction Foot path and Cycle Track (NMV) Package-2 [Bauxite Road to Ganesh Temple via Hanuman Nagar Circle and KLE School road]34.8526.99
25Construction Foot path and Cycle Track (NMV) Package-3 [APMC junction to AzamNagar Y-junction and Azam Nagar circle to Inmark Showroom]7.816.07
26Development of Mahatma Phule Garden, Tilakawadi.2.852.70
27Battery Operated Auto Rikshaws1.051.00
28Construction of 10 Bed Hospital at Vadagaon2.252.04
29Trauma Centre Part B1.151.15
30Roadside Drinking Water Kiosk Phase II0.600.55
31White Topping of Roads Package-2 [1. Ashoka Circle – Sangolli Rayanna Circle-Kittur Chennamma Circle-Bogarves Circle-Gogte Circle] [2. SP Office to Dharmanath Circle]44.6238.39
32UG LT [Package-4] Channamma Nagar & Tilakwadi Area6.867.28
33UG LT [Package-5] Shanti Nagar & Shivaji Colony Area6.536.93
34UG LT [Package-6] Maratha Colony & Nanawadi7.257.69
35UG LT [Package-7] 3rd Railway Gate to 1st Railway gate Area6.647.03
36UG LT [Package-8] Shukrawar Peth Road & Mahatma Phule Road Area7.297.73
37UG LT [Package-9] Dr. SPM Road & Lal Bahaddur Shastri Nagar Area7.618.08
38UG – LT Cabling with Decorative Poles (PAN) Package X : Bank of India to Basveshwar Circle (Khasbag)7.277.57
39UG – LT Cabling with Decorative Poles (PAN) Package XI : Basveshwar Circle (Khasbag) to Patson Ford Hossur6.486.74
40Smart Road with Paver Blocks at Shanti Nagar (Package 8)10.018.32
41Construction of Cycle track and Footpath NMV Package IV: Railway 4th Gate to Bemko Factory : 1km6.004.96
42Theme based Park Development : Saraf Colony1.090.97
43Theme based Park Development : Patwardhan Layout1.501.36
44Theme based Park Development : Nathpai Phase II0.900.85
45Heritage Park – Phase III3.182.12
46Smart Road with White Topping at Anagol road (Big Bazar To Medical Shop (Package 9): 1.2km12.1510.06
47Smart Road with White Topping at Vadgaon Road to Mahaveer Bhawan(Package 11) : 1.73km12.9310.71
48Smart Road with Paver Blocks at Tilakwadi, Vivekanad Colony and Marath Colony (Pkg-7)10.758.91
49White Topping of Roads Package-3 [1. BOI Circle – Nath Pai Circle-Vadagaon Circle-Navahind Society-RPD Cross-Tilakawadi First Railway gate] [2.Nath Pai- Kasturbai Balikashram-Goaves Circle]32.7427.2
50White Topping of Roads Package-4 [ Bank of India to Old PB Road]6.75.6
51Smart Road with Paver Blocks at Shastri Nagar, Kapileshwar Colony and Mahadva Road No 5 (Package 6): 9.5 km9.447.82
52Theme based Park Development : Shanti Nagar1.801.68
53Rehabilitation of Pigs (Compound Wall)0.260.25
54Rain Water Harvesting (ABD) and (PAN) Phase II0.900.82
55Improvement of Lakes : Kottekere Phase II3.002.76
Total773.90672.39

PROJECTS TENDERED (Rs. In Cr)

Name of the ProjectSCP CostTender Cost
1Smart Road with White Topping at Hotel Milan to Gandhi Statue Harsha Showroom(Package 10) : 1.73km17.3814.41
2Improvement of Lakes : Kottekere Phase I5.004.68
3Kottekere lake development Phase III2.301.90
4Construction of Roads with Paver Blocks at SBI Colony (R.C. Nagar) inBelagavi City Package-143.242.70
5Construction of Roads with Paver Blocks at Raghavendra Colony (R.C.Nagar) in Belagavi City Package-154.243.51
6Construction of Roads with Paver Blocks at Rani Channamma Nagar 1st Stage in Belagavi City Package-16,2.432.01
7Construction of Roads with Paver Blocks at Arjun Colony (R.C. Nagar) inBelagavi City Package-173.602.98
8Construction of Roads with Paver Blocks at Shastri Nagar -Balance Roads (North side of Mahatma Phule Road till Nalla) in Belagavi City Package-184.894.05
9Construction of Roads with Paver Blocks at Shastri Nagar-Balance Road (Behind Nartaki Theatre & Godse colony area) in Belagavi City Package- 19,4.823.99
10Up-gradation of Govt Library into Hi-tech Digital Library Phase-I1.371.13
11Construction of Roads with Paver Blocks in SV Road- Chidambar Nagar inBelagavi City Package-203.913.24
12Construction of Roads with Paver Blocks in Mrityunjaya Nagar in Belagavi City Package-213.913.24
Total57.0947.84

DPR STAGE

Name of the ProjectSCP CostDPR Cost
1Improvement of Parks and Gardens3.29
2Upgradation of Govt city library into Hitech of Digital Library (Phase- II-ICT)1.63
3Development of Anganawadi4.40
4Fort and Moat & Precinct (Phase I – Dredging and Cleaning)

Fort & Moat Phase II
25.00
5Smart road packages for ABD & Pan city38.96
6Extension of Art Gallery by Belagavi City Corporation6.00
7Smart Classroom Phase IV6.00
8NMT Zone & Hawkers zone (PAN)10.00
9Smart Classroom Phase III5.00
10ICT Phase II4.08
11Skill Development Center8.00
Total112.36
Grand Total SCM930.00
StatusSCPAmountW.O / DPR Cost
Projects Completed17.3115.17
Projects Ongoing773.90672.39
Projects Tendered57.0947.84
Projects in DPR Stage112.360.00
Projects in Concept Stage0.000.00
Total960.66735.40
PPP PROJECTS
Name of the ProjectSCP CostDPR Cost
1Multi Utility Facility Centres at Dharmnath Circle148.4145.09
2Energy Efficiency-LED Street Lighting63.9163.91
3Solar Roof Top – Phase I3.31.66
Total215.61210.66
1Public Bike Share9
Total9.00
Grand Total PPP224.61

CONVERGENCE PROJECTS

Name of the workDPR Cost (Rs Cr)Work Order Cost (Rs Cr)
1UG HT Line316.27316.27
2Swimming Pool2.752.75
3Badminton Court11
4Gymnasium1.51.5
5Neighborhood Park Development77
6Over Bridge on Kapileswar Road19.519.5
7Over Bridge on Old PB Road24.0524.05
8Rail Over Bridge at Old Gogte Road18.2518.25
9Primary & Secondary Drains14.314.3
10Public Urinals & Toilets1.51.5
11Pedestrian Friendly Pathway10.6510.65
12Carriage Way Improvement7070
13Providing Pavers in Shivaji Gardens in GYM Area and providing fountain in Mahatma Gandhi Garden0.350.35
14Construction & Development of steps in Lele Ground and Development of sambhaji Sports Ground in Mahadwar Road0.350.35
15Construction of Toilet and Gymnasium in near shivaji Garden0.30.3
16Development of Garden in Ramtheertha Nagar0.950.95
17Development of Garden in Mahantesh Nagar Sector No 80.450.45
18Providing Play Game materials in shri nagar park0.50.5
19Development of Garden in Ashok Nagar near Masjid0.40.4
20Construction of Play Ground in Sector N0-9 Malmaruthi Extension0.40.4
21Construction of Play Ground in Sector N0 2 Mahantesh Nagar0.40.4
22Construction of Play Ground in open space near srinagar Dweepad Road Side0.50.5
23Construction of Glass House at Mahantesh Nagar Garden0.30.3
24Construction of Children Garden in Samruddhi Colony(NEW) and Anand Nagar in Vadagoan0.30.3
25Development of Sport Ground in Shanti Colony and Development of Mahatma Phule garden in Tilakwadi0.30.3
26Construction of Samudaya Bhavan in ward No3 kaveri Nagar0.250.25
27Development of Garden near kanbargi siddeshwar temple0.30.3
28Development of Garden in Rukmini Nagar0.250.25
29Development of Garden in sadashiva nagar near ganapati temple and shivalaya0.40.4
30Development of Garden near Sunil Nayak Houe in jadav nagar0.950.95
31Development of open space garden near Bhate house in hanuman Nagar0.950.95
32BUDA scheme No-13-Development of garden in open Space0.50.5
33BUDA scheme No-51 -of Garden in open space near Barade House 0.950.95
34Development of Garden in open space in site N0 590 & 591 0.50.5
35Development of Garden in Basava Colony and Providing pavers in the garden near Bhate House Hanuman Nagar 0.550.55
36 Development of Garden in Devaraj Aras Colony 0.5 0.5
37 Construction of Play Ground in Sangameshwar Nagar 0.5 0.5
38 Construction of Hockey Stadium in Camp Area 0.95 0.95
39 Construction of play Ground in Government School in Vishweshvariah Nagar and Police Head Quaters ,Kanabargi &; Cantonment Area 0.4 0.4
40 BUDA scheme No-51 – Construction of Glass House in open Space 0.4 0.4
41 Construction of library Building & Chavadi Building in Kanabargi 0.5 0.5
42Construction of Art Gallery at Mahantesh Nagar 22
43City Gas Distribution 9090
44Construction of Mother Teresa memorial in shahu Nagar Belgaum 0.450.41
45Rejuvination of well in camp CEO house back side and fixing of filter unit in Belgavi 0.250.25
46Providing & fixing Electrical Poles at Middle of road from corporation Border to project no 47,Bauxite Road to hanuman nagar, APMC cross, 4.264.26
47Providing and fixing UG cables, CCTV, and street light arrangement at Ujwal nagar ,jadav nagar, sambaji gali gandhi nagar Belagavi,5.75.7
48Providing & fixing light poles Flood lights to play ground in thillakawadi 1) lele ground 2)Vaccaine Dept ground 2) vaccine Ground 3) Main road sambagi road. 1.191.19
49Construction of RCC Drain in Sambhaji galli Belagavi, kaplilewar colony,improvement of footpaths chennappa circle ,Koplapur circle 2.742.74
50Construction of Drain from Meenakshi bhavan Ghogte girls school,Bharath nagar ward no 15,Manhantesh Nagar,Ramathirtha galli,,khanburgi 8.718.71
51 Strom Water: construction of CD at 2nd cross New Goodshed,vadagav,kaplmeswar road,Mahaveer nagar,,Annapuranna wadi Belagavi 8.958.95
52 Lake Development:improment of Nala near zopad patti khonavalli galli,shrinagar 9.09.0
53 Burial Ground: improvement to Road and constructions of foot path from mahanth bavan to High way 0.750.75
54 Parks: improvement of open space in gokak road to datta mandir cross TC line under ,consrutions of new children park in samrudhi colony 0.620.62
55 Roads: improvements of roads and construction of gutter in kalamath Road ,Jadav Road, Rail Nagar,chikku bagh road, Markendeya road. vidya Nagar 93.9193.91
56 others-construction walls at CTC no 9674 in place of constructions of swimming pool area Ashok nagar ,installation of Effluent in fish market, Mutton market, Providing electrical supply at cricket stadium, installation of national Flag at kotekeri lake, 11.3911.39
57 others works -construction of swimming Pool at open Space in sector No .51 Belagavi,hanuman Nagar,walking line Maala Maruthi Layout,Hockey stadium ,contstruction of glass house in mahantesh nagar,Commericial shops at APMC road,PMC for urban infra structure,Development of Zoo in Butarmati Belgavi 11.3911.39
58 Under ground drainage: construction of CC in ashraya colony of Rukmini nagar ,slab at kalmath road 2.772.77
59 Parks: improment of Parks Rammurthy nagar ,Manhantesh nagr,shiv temple at sadashiv nagar ,Ashoka nagar 5.15.1
60 Roads: improvements of Roads and providing decorative street lights in fort area ,Bungalow area ,Bijapur colony ,shivtheratha colony 2020
61 Streetlight-udaymag in Khanapur Road, 4th railway gate 1.811.81
62 Construction of Minorities Moulana Azad Abdul Kalam Bhavan , Minorities Moulana azad Model School Part 1 and Part 2, Minorities Girls P.U. College, Minorities staff Quarters 3.843.84
63 Improvement of Road at Mannata Nagar and Cc Road at Sadashiv Nagar. CC Road at Azad Nagar and Azad Galli and at Devraj arasa Colony. Bogar Colony and Mahaveer Colony and CC Drain at Bagwan Galli, at Jalgar Galli and Aman Nagar. Nizamuddin Galli of New Gandhi Nagar at Gulzar Galli and Pavers at Azad Nagar and UGD at Aman Nagar. Improvement of Road at Piranwadi, at Machhe GramPanchayat. 3.883.88
64 Minorities Girls P.U.College and Hostel Building, Post Matric Girls Hostel,Post Matric Boys Hostel, Ramteerth Nagar at Swami Layout, Macche,Ramteerth Nagar, New Veer Bhadranagar, Rukmininagar,Vibhavnagar, Gandhi Nagar M.U.G.S-1, Khanzar Galli, Belagavi. 19.7719.77
65 Avenue plantation 10.92
66 Police Housing Corpoartion,1)construction of police station (Grade – 5) at shahapur in Belagavi under DC-Modernization ,2)construction of Barracks/Multipurpose Hall with infrastructure Facilities for KSRP 2nd Battalion at APMC Kangarallii in Belagavi District under 2017-18 state Budget Scheme. 3)Construction of 72 Police Quaters (60 PC & 12 SI ) including External infrastructure works for DPAR atPolice Head quaters in Belagavi and 78 quaters 35.1435.14
67 Belagavi Dist.co.op.Milk Producers Societies Union LTD,Mahantesh Nagar,Belagavi 0.30.3
68 Design and Supply of 5 ton per hour capacity multy fuel boliler andrelated works for Bemul dairy (KMF) 1.871.87
69 KMF-Flexi_Pack_Project at Belagavi 2121
70 Civil works for Refrigeration ,Upgradation of Main Dairy-KMF 0.260.26
71 Improvement Works to Depot No.3 at Belagavi 1.51.49
72 Construction of Commercial shops at vaccine Depot , Corporation Open Space of APMC Road widening of road in Belagavi. 4.124.12
73 Provisioning of Solar panel(SRTPV System) under IDPS Project 1.551.5
74 Improvement of Khanapur Road (NH-4.A) CH-5.55 to 6.60 km.in Belagavi 4.985.32
75 Construction of Khanapur Road (NH-4.A),3rd Railway Gate to RPD Cross,CH-2.20 to 3.40km.in Belagavi 6.816
76 Construction of Khanapur Road (NH-4.A),Belagavi-Panaji road, Chainage 3.40 to 4.25 km. in Belagavi 5.515
77 Construction of Khanapur road (NH-4.A),Belagavi-Panaji roadChainage 5 to 6.60 km. in Belagavi 5.455
78 Construction of Khanapur road,(Belagavi-Panaji Road), (NH-4.A), 3 rd Railway gate to Piranawadi Cross, Chainage 3.40 to 6.60 km.in Belagavi. 8.768
79 Construction of Khanapur road, (Belagavi to Panaji road) (NH- 4.A),RPD Cross to 3rd Railway gate, Chainage 2.20 to 3.40 km. inBelagavi. 4.854.5